TIMELINE

Council officers confirm outline timetable for Consultation

Jan 19th 2016 – ETS Committee – Approval for consultation work – Days / times and Area

March – Initial consultation to residents

May / June – ETS Committee – approval for detailed design consultation

Summer – Detailed design consultation

October – ETS Committee approval for traffic order

November / December – traffic order advertised

Jan 2017 – ETS Committee – final approval.

Feb / March – implementation work

Spring 2017 – Operational start